Senate has summoned the Minister of Finance, Budget and National Planning, Zainab Ahmed and the Accountant General of the Federation, Ahmed Idris, together with the Managing Director of the NSIA, Uche Orji and contractors to appear before it and explain the difference in the cost of major Federal roads being executed through the Nigeria Sovereign Investment Authority (NSIA).
The Committee Chairman, Senator Olamilekan Adeola Yayi in an interactive session with the MD, NSIA said discussion is of high importance in other to correct the mindset of people as regard funding of the road projects and variations in the cost of the project.
The road project which was tagged Legacy Projects includes Second Niger Bridge, Abuja – Kano Expressway, and Lagos – Ibadan Expressway are funded through tripartite agreement between the ministries of Finance, Works and the NSIA.
“On the issue of funding, by virtue of the information at my disposal and by what the Finance Minister made me understand, is that you are playing critical roles by providing funds for the legacy projects.
“As of today, two years down the line, only $300m is in the books as having been spent on the projects, this gives cause for concern.
“We believe that funding is critical to these projects. If the funding is not there, there is no way we can achieve those time frame that you have set out for the completion of the projects.
“On that note, we would be bringing on board, the Minister of Finance, the Minister of Works and Housing, the Managing Director of the NSIA, the Accountant General of the Federation, and the contractors who should be invited by the Minister of Works.
“I know there are variations already but we want to know the value and the scope of works that the variations cover. We want to know it because we don’t have it. That is why we want to know the actual value for the Lagos-Ibadan expressway, for the Abuja-Kaduna-Kano and for the second Niger bridge.”
Recall the Managing Director of NSIA, Uche Orji informed the lawmakers that his agency has no details of the cost of some of the projects.
Orji in response to a question on the actual cost of the rehabilitation of the Lagos-Ibadan expressway said only the Ministries of Works and Finance could provide the information needed by the Senators.
“Every day we argue out the issue of variation because any slight change affects my budget because I have a number that I’m working towards.
“Any change in the scope of work is a problem for us. I can’t answer some of the questions that border on variation and events that took place before I took over.
“We need to sit down with the active players in the award of the historical contract preceding our entrance.”
Olaoluwa Adekunle